Contract Agreement Amount
Rs. 1,10,59,394
Physical Progress
41.00%
Financial Progress
41.01%
Remaining Payment
Rs. 58
Surface Dressing and Shoulder Maintenance works (Periodic Maintenance) along Kamala-Dhalkebar section (MRM) (KM 236+630 to KM 257+000)
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 078-79
Contract Date: 2-May-22
Start Date: 2-May-22
Completion Date: 14-Jul-2022 (EOT Not Done)
Project Description
No description available.