Contract Agreement Amount
Rs. 74,84,924
Physical Progress
0.00%
Financial Progress
40.93%
Remaining Payment
Rs. 59
Roadway Excavation, Gabion and Stone Soling Work Along Heluwabeshi- Bumlingtar- Budhabare Road Section of Leguwa Tumlingtar Heluwabeshi Bumlingtar Budhabare Solu road Package III (Chainage: 2+240 to 3+340)
Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)
Fiscal Year: 076-77
Contract Date: 25-Sep-20
Start Date: 25-Sep-20
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.