Contract Agreement Amount

Rs. 7,69,88,381

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Rigid Pavement, Structural and Drainage Works at ch. 9+000 to 10+040 along Mirchaiya Katari Ghurmi Road, Udaypur.

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 079-80

0.00%

Contract Date: 3-Jul-23

Start Date: 3-Jul-23

Completion Date: 02-Jul-2024 (EOT Not Done)

Project Description

No description available.