Contract Agreement Amount

Rs. 2,46,57,309

Physical Progress

0.00%

Financial Progress

39.89%

Remaining Payment

Rs. 60

Construction Of RCC Multi Cell Box Bridge (2x10*x5) Over Dudhamati River along Dhota Tole Janakpur Na.Pa. 19-21 Jodne, Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 077-78

0.00%

Contract Date: 14-Mar-21

Start Date: 14-Mar-21

Completion Date: 04-Apr-2023 (EOT Done)

Project Description

No description available.