Contract Agreement Amount

Rs. 7,25,28,962

Physical Progress

90.00%

Financial Progress

39.79%

Remaining Payment

Rs. 60

Road Improvement Works on Gulariyaghat Bhajani Bude Road, Kailali

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

90.00%

Contract Date: 10-Jul-17

Start Date: 10-Jul-17

Completion Date: 09-Jan-2021 (EOT Done)

Project Description

No description available.