Contract Agreement Amount

Rs. 44,86,959

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Rigid Pavement works along Basbariya Gaupalika Manpur dekhi Parpurwa Sastra Camp hudain Bagmati Pul Sadak, Sarlahi

Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)

Fiscal Year: 081-82

0.00%

Contract Date: 20-Oct-24

Start Date: 20-Oct-24

Completion Date: 15-Mar-2025 (EOT Not Done)

Project Description

No description available.