Contract Agreement Amount
Rs. 40,78,990
Physical Progress
39.14%
Financial Progress
39.15%
Remaining Payment
Rs. 60
Roadway Excavation (Track Open) and Structure works on Rikhakoti Kuyapani pakki Karnali Nadi Pachaal Jharana Ga Pa ra palata Ga Pa 2 Kalikot
Office: हेभिईक्युपमेन्ट डिभिजन, काठमाण्डौ (39)
Fiscal Year: 079-80
Contract Date: 15-May-23
Start Date: 15-May-23
Completion Date: 14-May-2024 (EOT Not Done)
Project Description
No description available.