Contract Agreement Amount
Rs. 80,85,067
Physical Progress
0.00%
Financial Progress
39.07%
Remaining Payment
Rs. 60
Roadway Improvement Works(Ch. 05+000 to 14+000), Lashi to Syalagadi Gaun section of Jumla Bajar - Syalagadi Gaou- Chotra-dolpa Road
Office: डिभिजन सडक कार्यालय, जुम्ला (179)
Fiscal Year: 076-77
Contract Date: 15-Jun-20
Start Date: 15-Jun-20
Completion Date: 05-Jan-2021 (EOT Done)