Contract Agreement Amount

Rs. 1,60,94,364

Physical Progress

0.00%

Financial Progress

39.00%

Remaining Payment

Rs. 61

Bridge Maintenance works ( Bakeya, Pasaha and Balganga Bridge) along Dhansar- pathalaya section of MRM

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 078-79

0.00%

Contract Date: 2-Jan-22

Start Date: 2-Jan-22

Completion Date: 14-Jan-2023 (EOT Done)

Project Description

No description available.