Contract Agreement Amount

Rs. 9,96,56,483

Physical Progress

38.79%

Financial Progress

38.79%

Remaining Payment

Rs. 61

Construction of Two-Webbed RCC prestressed Bridge over Balawa Nadi along Inrarwa-Sabaila Road, Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 076-77

38.79%

Contract Date: 12-Apr-21

Start Date: 12-Apr-21

Completion Date: 17-Oct-2023 (EOT Not Done)

Project Description

No description available.