Contract Agreement Amount
Rs. 2,29,46,435
Physical Progress
38.72%
Financial Progress
38.72%
Remaining Payment
Rs. 61
Construction Of RCC Multi Cell Box Bridge (2x10*x5) Over Budho Kholsi (RDJKR/33701122/077-78/47
Office: यान्त्रिक कार्यालय, भक्तपुर (47)
Fiscal Year: 077-78
Contract Date: 3-Nov-21
Start Date: 3-Nov-21
Completion Date: 02-Nov-2022 (EOT Not Done)
Project Description
No description available.