Contract Agreement Amount

Rs. 80,30,59,033

Physical Progress

39.00%

Financial Progress

38.68%

Remaining Payment

Rs. 61

idening and Upgrading of ChauriKhola-Dolalghat Road (Chainage 0+000 to 25+580) Kavrepalanchok

Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)

Fiscal Year: 079-80

39.00%

Contract Date: 21-Sep-22

Start Date: 21-Sep-22

Completion Date: 05-Sep-2025 (EOT Not Done)