Contract Agreement Amount

Rs. 1,57,19,059

Physical Progress

35.00%

Financial Progress

38.68%

Remaining Payment

Rs. 61

Road protection works on Hetauda-Bhaise Palung TRP section

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 078-79

35.00%

Contract Date: 31-Dec-21

Start Date: 31-Dec-21

Completion Date: 04-Jul-2022 (EOT Not Done)

Project Description

No description available.