Contract Agreement Amount

Rs. 1,11,11,287

Physical Progress

46.91%

Financial Progress

38.48%

Remaining Payment

Rs. 61

BasgadhiLausaGajediBajar-KanchanpulLumbiniSadak and Londihiwa-Jogada-masina-Goglaha-Mosad-Bharat SimanaSadak

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

46.91%

Contract Date: 17-Nov-19

Start Date: 17-Nov-19

Completion Date: 13-Apr-2023 (EOT Done)

Project Description

No description available.