Contract Agreement Amount
Rs. 5,40,77,035
Physical Progress
0.00%
Financial Progress
38.29%
Remaining Payment
Rs. 61
Design & Build of 4 bridges on Rapti Rajmarg
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 069-70
Contract Date: 9-Jul-13
Start Date: 17-Jul-13
Completion Date: 07-Jul-2015 (EOT Not Done)
Project Description
No description available.