Contract Agreement Amount

Rs. 9,39,93,277

Physical Progress

40.00%

Financial Progress

38.09%

Remaining Payment

Rs. 61

Construction of Myagdi Khola Bridge at Singa Tatopani

Office: Road Division, Baglung (254)

Fiscal Year: 073-74

40.00%

Contract Date: 8-Jun-18

Start Date: 8-Jun-18

Completion Date: 07-Jun-2020 (EOT Not Done)

Project Description

No description available.