Contract Agreement Amount
Rs. 55,24,319
Physical Progress
0.00%
Financial Progress
38.07%
Remaining Payment
Rs. 61
Construction of Road Works on Ra Na Pa Nippani chowk Baghmara Dovan sauraha Road Chitwan
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 076-77
Contract Date: 13-Nov-19
Start Date: 13-Nov-19
Completion Date: 09-Jul-2020 (EOT Not Done)