Contract Agreement Amount

Rs. 1,03,07,005

Physical Progress

30.00%

Financial Progress

37.85%

Remaining Payment

Rs. 62

Construction Of Drain, RCC Pavement and pavement works along Ankuram Academy Purwa - Paschim Road, Bharatpur

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 079-80

30.00%

Contract Date: 14-Mar-23

Start Date: 14-Mar-23

Completion Date: 05-Jul-2023 (EOT Not Done)

Project Description

No description available.