Contract Agreement Amount

Rs. 17,61,41,925

Physical Progress

45.00%

Financial Progress

37.82%

Remaining Payment

Rs. 62

Road upgrading works at Sirutar Balkot Dadhikot Gundu Katunje Sipadol Ghyampedanda Nankhel Chitapol Tathali Road

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 078-79

45.00%

Contract Date: 24-May-22

Start Date: 24-May-22

Completion Date: 17-May-2024 (EOT Not Done)

Project Description

No description available.