Contract Agreement Amount
Rs. 3,92,43,410
Physical Progress
60.65%
Financial Progress
37.75%
Remaining Payment
Rs. 62
Construction of Two Webbed RCC Deck Slab Bridge in Fufrighat Bridge, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 074-75
Contract Date: 13-Jul-18
Start Date: 13-Jul-18
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.