Contract Agreement Amount

Rs. 96,53,044

Physical Progress

60.00%

Financial Progress

37.68%

Remaining Payment

Rs. 62

Pavement Work including Cross drainage and retaining Structures along Koshi-3 Jamuwa Chowk ward no 7 Kubhayahi hudai ward no-7 haripur Chowk sadak, Sunsari

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

60.00%

Contract Date: 3-Jan-22

Start Date: 3-Jan-22

Completion Date: 13-Jan-2023 (EOT Done)