Contract Agreement Amount

Rs. 7,28,40,712

Physical Progress

40.00%

Financial Progress

37.62%

Remaining Payment

Rs. 62

Roadway Excavation & Structure works along Sirshakali Dhungey 3 Simalta Parigaun Road, Dadeldhura

Office: कोशी पुल¸चतरा योजना, धरान (65)

Fiscal Year: 078-79

40.00%

Contract Date: 1-Aug-22

Start Date: 1-Aug-22

Completion Date: 01-Dec-2023 (EOT Not Done)

Project Description

No description available.