Contract Agreement Amount
Rs. 1,66,22,456
Physical Progress
37.00%
Financial Progress
37.49%
Remaining Payment
Rs. 62
Structural and pavement works along Alternative Route, Balde, Bajura
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 080-81
Contract Date: 26-Jan-24
Start Date: 26-Jan-24
Completion Date: 29-Jun-2024 (EOT Not Done)
Project Description
No description available.