Contract Agreement Amount
Rs. 19,23,11,333
Physical Progress
40.00%
Financial Progress
37.37%
Remaining Payment
Rs. 62
Construction of Prestressed Concrete Bridge(3x35m) with Pile Foundation at Madhuwan-Khamhuwa over Pasaha River, Bara
Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)
Fiscal Year: 079-80
Contract Date: 4-Dec-22
Start Date: 4-Dec-22
Completion Date: 13-May-2025 (EOT Not Done)
Project Description
No description available.