Contract Agreement Amount

Rs. 6,89,45,813

Physical Progress

0.00%

Financial Progress

37.33%

Remaining Payment

Rs. 62

Major Maintenance and safety works of SRN Bridges (Charnath, Baluwa, Jagadev Branch, Jagadev, Jalad , Aurahi and Basai) along East -West Highway

Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)

Fiscal Year: 077-78

0.00%

Contract Date: 19-Mar-21

Start Date: 19-Mar-21

Completion Date: 19-Mar-2022 (EOT Not Done)

Project Description

No description available.