Contract Agreement Amount

Rs. 53,81,635

Physical Progress

40.00%

Financial Progress

37.01%

Remaining Payment

Rs. 62

Sahasradhara-Tara-Tatarkot dhekhi Banau jane Sadak,Parbat

Office: Road Division, Baglung (254)

Fiscal Year: 076-77

40.00%

Contract Date: 28-Dec-19

Start Date: 28-Dec-19

Completion Date: 25-Mar-2020 (EOT Not Done)

Project Description

No description available.