Contract Agreement Amount

Rs. 76,83,98,187

Physical Progress

36.00%

Financial Progress

34.94%

Remaining Payment

Rs. 65

Upgrading/Improvement of Sahadatsthal-Shantinagar Section of Madan Bhandari Highway to Blacktopped Standard

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 079-80

36.00%

Contract Date: 9-Nov-22

Start Date: 9-Nov-22

Completion Date: 05-May-2025 (EOT Not Done)

Project Description

No description available.