Contract Agreement Amount

Rs. 25,96,341

Physical Progress

0.00%

Financial Progress

34.93%

Remaining Payment

Rs. 65

दाङ सिमेण्ट फ्याक्ट्री क्वायरी साइट

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 073-74

0.00%

Contract Date: 20-Feb-17

Start Date: 20-Feb-17

Completion Date: 26-Dec-2017 (EOT Done)

Project Description

No description available.