Contract Agreement Amount

Rs. 78,48,100

Physical Progress

0.00%

Financial Progress

34.77%

Remaining Payment

Rs. 65

Rapti Highway (Dubaish Khola - Ramri Section 40+000 to 46+000) in Dang District.

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 078-79

0.00%

Contract Date: 6-Mar-22

Start Date: 6-Mar-22

Completion Date: 09-Jul-2022 (EOT Not Done)

Project Description

No description available.