Contract Agreement Amount
Rs. 2,12,59,950
Physical Progress
0.00%
Financial Progress
34.65%
Remaining Payment
Rs. 65
मिर्चैया कटारी घुर्मी सडक (मिर्चैया कटारी खण्ड)
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 074-75
Contract Date: 9-May-18
Start Date: 11-May-18
Completion Date: 04-Jul-2018 (EOT Not Done)
Project Description
No description available.