Contract Agreement Amount
Rs. 23,64,50,089
Physical Progress
75.00%
Financial Progress
34.50%
Remaining Payment
Rs. 65
Construction of RCC Bridge over Dhoda Nadi Bridge Kaj Bhakunda Road, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 071-72
Contract Date: 10-Jan-16
Start Date: 10-Jan-16
Completion Date: 09-Jan-2019 (EOT Not Done)
Project Description
No description available.