Contract Agreement Amount
Rs. 62,94,311
Physical Progress
33.00%
Financial Progress
34.15%
Remaining Payment
Rs. 65
Road Construction work along Ramdhuni Baithar Kutipur Barahachettra Aitabare Chakraghati Sadak, Sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 078-79
Contract Date: 20-Apr-22
Start Date: 20-Apr-22
Completion Date: 15-Jul-2023 (EOT Done)
Project Description
No description available.