Contract Agreement Amount

Rs. 2,40,07,048

Physical Progress

35.00%

Financial Progress

34.05%

Remaining Payment

Rs. 65

Construction of Bonga Dobhan Motorable Bridge, Baglung District (1*20m)

Office: हेभिईक्युपमेन्ट डिभिजन, वांके (41)

Fiscal Year: 076-77

35.00%

Contract Date: 31-Dec-20

Start Date: 31-Dec-20

Completion Date: 13-Apr-2023 (EOT Done)

Project Description

No description available.