Contract Agreement Amount

Rs. 43,45,25,408

Physical Progress

34.01%

Financial Progress

33.84%

Remaining Payment

Rs. 66

Upgrading of Road to blacktop standard with Roadway Excavation, Structural and Drainage Works in Saleti-Uku-Joljibi-Bet Section of Mahakali Corridor (CH: 257+000 to CH:269+318) Rajendra Nirman Sewa Pvt.ltd (MCRP/33701103/078/79-07

Office: दार्चुला टिङकर सडक योजना, दार्चुला (106)

Fiscal Year: 078-79

34.01%

Contract Date: 4-Jul-22

Start Date: 4-Jul-22

Completion Date: 04-Jul-2025 (EOT Not Done)

Project Description

No description available.