Contract Agreement Amount

Rs. 3,26,16,237

Physical Progress

33.76%

Financial Progress

33.79%

Remaining Payment

Rs. 66

Rehabilitation Works of Post Monsoon Damaged Section on Surkhet Dahikhola Section of Karnali Highway(Chainage:75+000 to 115+000)

Office: हेभिईक्युपमेन्ट डिभिजन, काठमाण्डौ (39)

Fiscal Year: 079-80

33.76%

Contract Date: 17-May-23

Start Date: 17-May-23

Completion Date: 05-Jul-2023 (EOT Not Done)

Project Description

No description available.