Contract Agreement Amount

Rs. 11,49,12,920

Physical Progress

34.00%

Financial Progress

33.42%

Remaining Payment

Rs. 66

Design &Build of Kamalamai Na pa .10 Dovan ma parne Chadaha Kholama pul:Sindhuli

Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)

Fiscal Year: 077-78

34.00%

Contract Date: 26-Aug-20

Start Date: 26-Aug-20

Completion Date: 23-May-2023 (EOT Not Done)

Project Description

No description available.