Contract Agreement Amount

Rs. 59,46,413

Physical Progress

0.00%

Financial Progress

32.72%

Remaining Payment

Rs. 67

Blacktopped Road Construction Works including Drainage Structures along Laxminiya - Sohal Jahada 4-Rajbansi tole hudai-Kadmaha hudai-Nocha sima Sdak Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 075-76

0.00%

Contract Date: 11-Apr-19

Start Date: 11-Apr-19

Completion Date: 30-Jun-2019 (EOT Done)

Project Description

No description available.