Contract Agreement Amount
Rs. 20,02,872
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Specific Maintenance of Mahakali Highway (Chainage 15+000 to 68+000, Kailali)
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 29-Jun-20
Start Date: 6-Jul-20
Completion Date: 28-Mar-2021 (EOT Not Done)
Project Description
No description available.