Contract Agreement Amount

Rs. 60,13,806

Physical Progress

32.00%

Financial Progress

32.02%

Remaining Payment

Rs. 67

Specific Maintenande works on Sanfe-Rakse-Martadi Road Section

Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)

Fiscal Year: 080-81

32.00%

Contract Date: 24-Dec-23

Start Date: 24-Dec-23

Completion Date: 12-Jun-2024 (EOT Not Done)

Project Description

No description available.