Contract Agreement Amount

Rs. 1,39,34,385

Physical Progress

33.00%

Financial Progress

31.22%

Remaining Payment

Rs. 68

(Rehabilitation works on Betrawoti Dhunche section of Betrawoti Syprubesi Road (Package-1).)

Office: हेभिईक्युपमेन्ट डिभिजन, वांके (41)

Fiscal Year: 079-80

33.00%

Contract Date: 18-Apr-23

Start Date: 18-Apr-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.