Contract Agreement Amount
Rs. 1,84,55,548
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of RCC Bridge over Gyamirekhola , Budhanilkhantha,1,4
Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)
Fiscal Year: 074-75
Contract Date: 3-May-18
Start Date: 3-May-18
Completion Date: 03-May-2019 (EOT Not Done)