Contract Agreement Amount

Rs. 3,85,72,568

Physical Progress

38.16%

Financial Progress

31.13%

Remaining Payment

Rs. 68

Construction of Blacktopped road Including Drainage Structures along Gramthan Ga.Pa-1 Dekhi milanchowk Hudai lakhantari, Gidhaniya, Dhobiyare hudai Haraincha sam, morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 076-77

38.16%

Contract Date: 26-Jul-20

Start Date: 26-Jul-20

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.