Contract Agreement Amount

Rs. 1,35,34,161

Physical Progress

31.00%

Financial Progress

30.96%

Remaining Payment

Rs. 69

Rehabilitaion Reconstruction works on Surkhet- Jumla Road , Dailekh( ch 100+000-132+000)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

31.00%

Contract Date: 30-May-21

Start Date: 31-May-21

Completion Date: 14-Jul-2021 (EOT Not Done)

Project Description

No description available.