Contract Agreement Amount
Rs. 4,89,99,920
Physical Progress
0.00%
Financial Progress
30.81%
Remaining Payment
Rs. 69
Roadway Excavation, Construction of Retaining structures on Marim -Tinje- Dho -Dunai Road, Dolpa
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 072-73
Contract Date: 22-Apr-16
Start Date: 22-Apr-16
Completion Date: 12-Jun-2020 (EOT Done)