Contract Agreement Amount

Rs. 1,29,32,340

Physical Progress

35.00%

Financial Progress

30.62%

Remaining Payment

Rs. 69

Road Improvement works of Panchkhal Palanchok Road (Ch.0+000 to ch.10+000)

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 078-79

35.00%

Contract Date: 3-Aug-22

Start Date: 3-Aug-22

Completion Date: 05-Jul-2023 (EOT Not Done)