Contract Agreement Amount
Rs. 19,76,515
Physical Progress
40.84%
Financial Progress
29.00%
Remaining Payment
Rs. 71
Blacktopped Road Construction work along Barahachettra Na. Pa ward no.9 Saipatri Chowk hudai Uttar Tarfa 16 no. ward kauwa tole, payari tole Rajabas paschhim Buspark Sadak, Sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 12-Nov-20
Start Date: 12-Nov-20
Completion Date: 15-Dec-2022 (EOT Done)
Project Description
No description available.