Contract Agreement Amount
Rs. 2,39,40,196
Physical Progress
0.00%
Financial Progress
27.79%
Remaining Payment
Rs. 72
Construction of Simply Supported,25m Span, Cast-in-situ, 2-Webbed Reinforced Prestressed Concrete Bridge over Chyatra Khola,Rapti Na Pa 11, Chitwan
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 074-75
Contract Date: 27-May-18
Start Date: 27-May-18
Completion Date: 27-May-2018 (EOT Not Done)
Project Description
No description available.