Contract Agreement Amount
Rs. 90,82,199
Physical Progress
35.00%
Financial Progress
27.66%
Remaining Payment
Rs. 72
Improvement of Masuriya-Hasuliya Road,Kailali (1+300 To 2+500 From Surminala Bridge Hulaki Sadak)
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 21-Jun-20
Start Date: 28-Jun-20
Completion Date: 28-Mar-2021 (EOT Not Done)
Project Description
No description available.