Contract Agreement Amount
Rs. 3,55,66,605
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of RCC Bridge Over Thiwa Khola along Dovan Olangchunggola Road, Taplejung
Office: उत्तर दक्षिण (मुलघाट दोभान ओलाङ्चुङगोला खण्ड) सडक योजना, ताप्लेजुङ्ग (288)
Fiscal Year: 074-75
Contract Date: 12-Jul-17
Start Date: 12-Jul-17
Completion Date: 11-Jan-2019 (EOT Not Done)
Project Description
No description available.