Contract Agreement Amount
Rs. 4,86,46,706
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of RCC Bridge Over Seuti Khola Along Koshi Highway, Sunsari District
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 064-65
Contract Date: 16-Jul-08
Start Date: 16-Jul-08
Completion Date: 30-Jun-2015 (EOT Not Done)
Project Description
No description available.